Belgian authorities have ordered Google to suspend construction of a data centre in the south of the country because of a lack of proper planning permission, a regional official said on Friday.

"We have identified a major offense: the illegal construction of a building covering three hectares," or 7.4 acres, Nicolas Yernaux, spokesman for the Wallonia regional authorities, told AFP.

The stop-work order at the former mining site covering some 50 hectares in total comes after the environmental group Greenpeace accused Google of carrying on construction despite lacking the correct permits. Inspectors visited the site on Thursday to inform Google representatives to halt construction.

The project, on a business park straddling Farciennes, Sambreville and Aiseau-Presles near Charleroi, has been locked in a legal dispute for months. Google began building under a permit issued in 2024, then applied to amend it — merging two planned buildings into one and switching the cooling system from air to water drawn from the nearby River Sambre.

The regional minister responsible for infrastructure, François Desquesnes, refused the amended permit in August, after a local resident appealed and amid public opposition over drought concerns. Greenpeace said the tech giant kept building even though the latest version of its planning permission had been revoked.

Google has challenged the refusal before Belgium's Council of State, the country's highest administrative court, with a hearing scheduled for early January. The company has not commented publicly on the stop-work order.

The Belgian order is the second time in two months that a European government has stopped work at a Google data centre site, as tech giants race to build capacity to support the artificial intelligence boom.